Which of the following is NOT a content of a change order?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

A change order is a formal document used in project management to request modifications or changes to the original project scope, contract terms, or conditions. It serves as an official agreement between the involved parties regarding the alteration of project details.

The final inspection report is not typically included in the content of a change order. Instead, the change order usually consists of key elements such as the date and time when approval was received, a detailed description of the change request itself, and written authorization that grants the permission to proceed with the change. Including these components ensures that all parties are aligned on the adjustments being made to the project, while the final inspection report is more related to the overall project completion and quality assessment rather than the approval process for changes.

Understanding this distinction is crucial for managing project changes effectively and maintaining clear documentation throughout the project lifecycle.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy