Which of the following is NOT part of the OSP design checklist?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

The choice that is not part of the OSP (Outside Plant) design checklist is field reports. The OSP design checklist typically includes critical elements that ensure the design meets the necessary standards and requirements.

The title block is essential as it contains vital project details, such as the project name, client information, and version control, which are all fundamental to the documentation process. The aerial environment is also a key consideration in the design checklist, addressing the conditions and factors that impact above-ground installations, such as tree heights, power lines, and other aerial obstacles. Required information is similarly important as it encompasses the specific data, specifications, and guidelines necessary for the successful execution and compliance of the project.

Field reports, while they may provide valuable insights during the project execution phase, are not typically included within the design checklist itself. This checklist focuses more on the planning and preparatory stages of the project rather than the documentation of observations or updates from the field during the construction or implementation phases.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy