Which item is NOT listed as part of the Acceptance Plan contents?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

The Acceptance Plan is a critical document that outlines the criteria and process through which a project’s components will be accepted upon completion. This encompasses various elements ensuring that all parties understand what is required for satisfactory completion.

The inclusion of items such as the date and time of tests and testing witnesses is essential because they provide a clear schedule and accountability during the testing process. Recording equipment calibration dates is equally important, as it assures that the tools used for testing are accurate and reliable, further validating the integrity of the acceptance tests.

Change order approvals, however, are generally not considered part of the Acceptance Plan contents. Change orders relate to modifications made to the original project scope, budget, or timeline and are typically documented separately as part of project management processes. These modifications may affect project execution but do not directly pertain to the acceptance criteria for the project’s testing phase.

In summary, the correct answer identifies an item that falls outside the specific focus of the Acceptance Plan, which is aimed at detailed testing outcomes and requirements rather than alterations to project parameters.