Which document includes as-builts, test results, and warranties in the OSP post construction phase?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

The completion package is a critical document that compiles all relevant information at the conclusion of a project. During the post-construction phase of an Outside Plant (OSP) project, it serves to bring together as-builts, which provide a detailed representation of the built infrastructure as it was actually constructed, along with test results that confirm the integrity and functionality of the installed systems. Warranties for various components are also included, ensuring that the project stakeholders have records for any necessary future claims or maintenance.

Having a completion package is essential because it encapsulates the totality of the project deliverables, ensuring that there is a clear reference for all aspects of the work completed. This document serves as a valuable resource for the operation and maintenance of the system moving forward, as it provides a comprehensive overview of what has been installed and its specifications. It also facilitates the transition from construction to operation by providing all necessary documentation, thus reducing any potential confusion or oversight during handover stages.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy