What timeframe do operations and maintenance typically begin in relation to post construction?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

Operations and maintenance typically begin before the end of post construction because this ensures that systems are functioning properly while final construction tasks are still being completed. Starting operations and maintenance early allows for any issues identified during the construction phase to be addressed proactively, rather than waiting until the project is fully completed. This approach minimizes disruptions and helps facilitate a smoother transition to regular operations.

Although choices regarding final payments, system turn-up, or cutover might imply a clear division between phases, initiating operations and maintenance prior to the end of construction can lead to increased efficiency, ensuring that personnel are ready to manage and support the systems as they come online. This proactive involvement helps in assessing performance, training staff, and preparing for any immediate operational needs, leading to a more seamless handover once construction is officially completed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy