What purpose does a field order serve during a construction project?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

A field order serves the purpose of facilitating minor changes during a construction project without significantly altering the original scope. This is particularly important because such changes often arise during the execution of project work due to unforeseen circumstances or the need for small adjustments that enhance efficiency or quality without necessitating a formal change order process.

Using field orders allows project managers and teams to respond quickly to necessary adjustments, ensuring that the project progresses smoothly while minimizing disruption. It provides a flexible mechanism for managing minor modifications and can help maintain project timelines and budgets by avoiding the more complex and lengthy change order procedures that are typically required for larger scope changes. This process helps to keep the work moving forward without losing sight of the overall project goals and objectives.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy