What is the primary purpose of Construction Administration Submittals?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

The primary purpose of Construction Administration Submittals is to serve as a communication form from the contractor to the owner. These submittals are vital for ensuring that the project remains aligned with the owner's expectations and project specifications. They facilitate the transfer of information regarding materials, equipment, and proposed methodologies for executing the work. This two-way communication helps the contractor to confirm that their approach meets the owner’s requirements, as well as to receive the necessary approvals for proceeding with specific aspects of the construction.

This process is essential for maintaining good coordination and collaboration throughout the project lifecycle, as it helps to clarify any project details that may be ambiguous or require further discussion. Submittals often include shop drawings, product data, and samples, all of which provide important details for the owner’s review and approval. This aspect makes them crucial for project success, ensuring that both parties are on the same page regarding expectations and deliverables.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy