In the Design-Build (DB) delivery method, what is a key feature?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

In the Design-Build (DB) delivery method, a key feature is the overlapping of construction and design phases. This approach allows for a more integrated process where the design and construction teams collaborate closely from the outset. By enabling concurrent execution, it can lead to time savings and increased efficiency, as adjustments can be made on the fly based on real-time feedback from construction activities.

This integration often results in improved communication and a streamlined workflow, mitigating the risks associated with the traditional design-bid-build method, where phases are distinctly separate. Such an approach not only enhances project timelines but can also lead to innovation in problem-solving, as builders can input their practical insights into the design process actively.

In contrast, having separate contracts for design and construction may lead to disjointed efforts, while awarding contracts to the lowest bidder does not guarantee that the project will meet the necessary quality or design standards. Additionally, completing the design before bidding limits flexibility and responsiveness to potential design improvements or construction methods that could be identified during the project execution.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy