During post construction, which of the following should the owner’s staff focus on?

Prepare for the BICSI Registered Telecommunications Project Manager Exam with our quiz. Test your knowledge through multiple choice questions, hints, and explanations to ensure success.

Focusing on learning the new system during post-construction is critical for the owner’s staff, as it ensures they are equipped to operate and maintain the newly implemented infrastructure effectively. As the project transitions from construction to operation, the staff must understand the functionalities, features, and operational protocols of the new system to uphold productivity and address any issues that may arise.

This training is fundamental not only for adequate system operation but also for maximizing the return on investment in the new technology or infrastructure. A thorough understanding of the system prepares the staff to troubleshoot potential problems, perform preventive maintenance, and utilize the system's capabilities to their fullest potential.

In contrast, concentrating on learning an old system would be counterproductive as it may not be relevant anymore, and focusing on moving out does not provide any value to the long-term operation and management of the new system. Overseeing contractor work, while important during construction phases, is not typically the primary concern for the owner's staff once the project is completed and handed over.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy